How the peak forecast works.
A peak charge is set by a handful of hours, the highest of a month or a season. This page describes how tinypeak estimates the chance that each remaining day sets that peak, and how those estimates are checked. As a worked example it follows ERCOT 4CP through August 2025, as the current model forecast it on the evening of August 19, replayed on the data archived for that evening.
What is forecast
A peak program bills on a few intervals of its window, its highest one or few. ERCOT 4CP counts the single highest of each month, here August, and the load in every other hour of August has no effect on that charge.
On the evening of August 19, the highest day so far was Monday, August 18, at 83.9 GW. The forecast addresses one question about that peak, namely whether any day still to come will exceed it.
Daily peak distributions
The peak load of a future day is uncertain, so the forecast gives each day a distribution rather than a single value. The distribution generally widens the further ahead the day lies.
Different sources inform it at different leads. For roughly the next week, it starts from the grid operator's own load forecast, corrected for that forecast's past errors. Out to about two weeks, it is driven by an ensemble weather forecast, in which each member is one plausible course of the weather. A load model fitted to the program's history converts each member into an expected peak for each day. Beyond two weeks, weather forecasts carry little skill, and each member continues from the temperatures usual for that time of year, keeping a share of its departure from them.
Around each member's expected peak, the model adds the load's own error, the part the weather does not explain. The day's distribution combines the two, and the day's chance of exceeding the current peak is the share of that distribution lying above it.
In member , the peak of day is taken to be normal, with mean and standard deviation , the load's own error once the weather is known, narrowed to the operator's error where that is smaller and widened for the difference between settled and live loads. The chance that it exceeds the current peak is
where is the standard normal survival function and , the average over the members, is the day's own chance. Beyond the operator's horizon, the mean comes from the load model, at the member's forecast high temperature . Each member's temperatures are first corrected for bias and spread at each lead where enough past forecasts exist.
Load rises with each degree above a cooling threshold and below a heating one, shifts with the kind of day and follows the season, around a level that is re-estimated each day. Read the other way, the model says how hot a day must be to reach the current peak. A load of 83.9 GW needs a high of about 100°F on a weekday and about 101°F on a Saturday, when load runs lower at any temperature.
Correlated forecast errors
The question concerns all the remaining days together, and their errors are not independent. The ensemble already links the days, since a member that runs hot tends to stay hot for the whole week. The load's own error is correlated as well, and a forecast that is too high one day is usually too high the next. Once the weather is known, the load's remaining error on consecutive days correlates at roughly 0.3 to 0.7 in summer across the markets covered, and less in some markets and seasons.
Treating the days as independent would make five warm days look like five separate chances at a new peak, and it would overstate the chance that the current peak is beaten.
The model therefore splits the load's error into two parts. One belongs to the day alone. The other is shared along a path through the month and decays from one day to the next. The split leaves each day's distribution as it was and changes only how the days vary together.
With a share of the error's variance shared, and the shared part decaying by a factor per day over a gap of days, the error on day is
where , and are standard normal. Both and are estimated for each season of the year, from the correlations, one and two days apart, of the load model's past errors given the weather that occurred. A further share of each day's spread is a single shift applied to the whole path, standing for the weather regime or a drift in the load level.
Survival of the current peak
The pieces are combined by simulation. Each ensemble member is split into four paths, 124 in all, and each path carries its own draw of the shared error through the rest of the month.
Once a path is fixed, the shared error is known and what remains of each day's error is independent of the other days. Each day's chance of exceeding the peak can then be computed for that path alone, and the chance that no day exceeds it is the product of the complements along the path.
The average of that chance over all paths is the probability tinypeak publishes. Because a path that runs hot does so on every day, a run of risky days counts largely as one threat rather than several. This is why the chance that the peak holds comes out higher than the product of each day's own chance.
49%
For path of member , with its draw of the shared error, the mean of day shifts and its spread shrinks to the day's own part.
The published chance is the product along each path, averaged over the paths.
Some programs bill on their top peaks. A current peak at rank keeps its place if no more than later days exceed it, and within a path that count follows a Poisson-binomial distribution.
Demand response
The days' expected peaks carry one correction, because peak programs change the load they measure. When a day looks likely to set the peak, large customers reduce their consumption, and the day's peak ends up lower than the weather alone would suggest. The model estimates from history how much the load falls at each level of expected risk. It treats the operator's forecast as not including that fall, so the fall is taken off both the operator's forecast and the load model's, in each path. On such days it also takes off the operator's usual overshoot, measured from past high-risk days.
The hour of the peak
A customer who curtails does so in particular hours, so the forecast also says which hours a day's peak is likely to fall in. The operator publishes an hourly forecast, and its errors are not independent from hour to hour. When it is too low at 16:00 it is usually too low at 17:00 as well, and neighbouring hours' errors correlate at about 0.95.
The model therefore draws the operator's hours together, with the error structure measured from its past forecasts, thousands of times. The chance that an hour sets the day's peak is the share of those draws in which it comes out highest, and the range for the day's peak is read from the same draws, so the two always agree.
On the current day, part of the peak has already been metered, so only the remaining hours are forecast, and the day's peak is the higher of the metered maximum and the forecast for the hours that remain. The meter also shows how the operator's forecast is doing. Where its recent miss has historically carried into the rest of the day, the remaining hours move by that amount and their range narrows. Late in the afternoon this cuts the error of the rest of the day's peak by a tenth to a half, depending on the market.
For days further ahead, the hour chances blend the operator's hourly shape with the hours the program's peaks have historically fallen in. The likely peak hours shown for a day are the shortest run of its remaining hours that holds at least 80% of the model's probability for when the day's peak falls among them.
One draw of a day's hours , which the operator forecasts at , is
where is the operator's bias at the lead and is the meter's carry. The standard deviations and the correlations , with Cholesky factor , are those of the operator's day-before errors, measured per season against the metered load. scales them to the error at the lead, and is a vector of independent standard normals. Four thousand draws are taken, seeded by the forecast's own inputs so a forecast can be reproduced. A program with no hourly forecast from its operator uses its historical peak-hour profile alone.
Daily updates
The forecast is republished every hour, and the curve below follows each evening's forecast. A day that ends below the current peak removes one opportunity to beat it, so the chance that the peak holds rises. A warmer forecast lowers it. When a higher peak is set, it becomes the new reference and the curve starts again from there.
By the end of August, few days remained and the chance approached certainty.
One exception applies. For some programs the billed load is not published in real time, and the forecast reads a public load in its place (AESO 12CP reads Alberta Internal Load). The two loads do not always rank days the same way, so the chance stays below certainty even after the window closes, while the leading days are close. The sources page reports how often the two loads agree.
Thresholds and calls
A probability is not by itself a decision. Turning it into one takes a threshold, and every day whose chance of setting the peak reaches the threshold is called. At 10%, the example evening calls one day, August 25.
The threshold is set in the header of the forecast page, and the evaluation scores the same threshold. tinypeak reports the call but does not turn it into an operating instruction.
Verification
Every forecast is stored unchanged, the 06:00, 12:00 and 19:00 forecasts for good and the hourly ones between them for 30 days. Each forecast is scored once its window closes, against the official peak where the operator has posted it and against the metered load until then. Forecasts that give a 37% chance should come true about 37% of the time when many comparable forecasts are pooled. The evaluation tests this calibration, and also whether the days that set the peak were ranked highest. It scores the hours too, how often the hour given the best chance held each day's peak, beside the hour the operator's own forecast put highest.
Every change to the model is replayed over past seasons on the data archived for each moment, and it is adopted only when the pooled record shows that it helps. Live forecasts are kept separate from replayed ones, and results from different model versions are never mixed.