What is PJM NSPL · PPL?
A zone's single highest hour from November to October sets the next year's transmission charge. PJM takes each transmission zone's highest hour of load from November to October, on any day, winter included. That hour sets how the zone's transmission cost is shared in the next calendar year. Many utilities then split it among customers by peaks of their own, each a separate program here.
At a glance
One peak hour each year from November 1, any day, measured hourly. Measured on PPL (with UGI and Allegheny Electric Cooperative) transmission zone load, in Eastern time.
What a peak costs
At published prices, a MW in the counted peaks costs about $110,000 a year. It is the price per MW of the charge, not a customer's bill, which its utility or supplier sets.
- $112,973 per MW-year, from Aug 1, 2026Annual Transmission Revenue Requirements and NITS Rates, as of 8/1/2026 ↗
What we forecast
Once PJM's data is connected, we forecast each zone's hourly load and the chance that each day holds its peak.
Where the forecast simplifies
- Transmission owners can adjust a zone's posted value, so history uses PJM's posted figure, not one rebuilt from metered load.
- The small OVEC zone is not forecast, because PJM publishes no load data for it.
Sources
- The rulePJM Manual 27 §5.2.1–5.2.2 (Rev 103) ↗PJM
- The official peaksPJM Network Service Peak Loads (NSPL) for 2026 ↗PJM
- Our load dataData Miner API Guide (2026) ↗PJM
Checked against these documents Sep 24, 2026.