Peak charges explained

What is PJM NSPL · AECO?

A zone's single highest hour from November to October sets the next year's transmission charge. PJM takes each transmission zone's highest hour of load from November to October, on any day, winter included. That hour sets how the zone's transmission cost is shared in the next calendar year. Many utilities then split it among customers by peaks of their own, each a separate program here.

At a glance

  • Transmission charge
  • Peak hour
  • Zone peak
  • Billed from next January
The whole yearNovDecJanFebMarAprMayJunJulAugSepOct

One peak hour each year from November 1, any day, measured hourly. Measured on Atlantic City Electric transmission zone load, in Eastern time.

What a peak costs

At published prices, a MW in the counted peaks costs about $86,000 a year. It is the price per MW of the charge, not a customer's bill, which its utility or supplier sets.

What we forecast

Once PJM's data is connected, we forecast each zone's hourly load and the chance that each day holds its peak.

Where the forecast simplifies

  • Transmission owners can adjust a zone's posted value, so history uses PJM's posted figure, not one rebuilt from metered load.
  • The small OVEC zone is not forecast, because PJM publishes no load data for it.