What is PJM Dominion 12CP · DOM?

Dominion splits its zone's transmission cost by load at the zone's twelve monthly peaks. Dominion splits its zone's transmission cost among customers by their average load at the zone's highest hour in each of the twelve months ending September 30. Every day counts, winter mornings included, and the share applies from January to December of the next year.

At a glance

  • Transmission charge
  • Peak hour
  • Zone peak
  • Billed from next January
A peak each monthOctNovDecJanFebMarAprMayJunJulAugSep

One peak day each month, any day, measured hourly. Measured on Dominion transmission zone load, in Eastern time.

What we forecast

Once PJM's data is connected, we forecast the Dominion zone's hourly load and the chance that each day is its month's peak.

Where the forecast simplifies

  • Dominion's Virginia-only share is split out separately and is not forecast.