What is PJM ComEd capacity PLC (hybrid) · COMED?

ComEd's capacity tag blends PJM's five summer peaks with ComEd's own five. ComEd sets a customer's capacity tag from its average load in PJM's five summer peak hours. When the customer's load in ComEd's own five summer peaks is higher, part of the difference is added. The tag applies for the year from the next June.

At a glance

  • Capacity charge
  • Top 5 days
  • Market and zone peaks
  • Billed from next June
One seasonJanFebMarAprMayJunJulAugSepOctNovDec

Top 5 peak days each season, June 1 to September 30, any day, measured hourly. Measured on ComEd transmission zone load, in Eastern time.

What we forecast

This program has no forecast of its own. Its two parts are forecast by the PJM 5CP and ComEd transmission programs.

Where the forecast simplifies

  • How much of the difference is added is set after the summer from every customer's loads, so it cannot be known ahead.