What is PJM ComEd capacity PLC (hybrid) · COMED?
ComEd's capacity tag blends PJM's five summer peaks with ComEd's own five. ComEd sets a customer's capacity tag from its average load in PJM's five summer peak hours. When the customer's load in ComEd's own five summer peaks is higher, part of the difference is added. The tag applies for the year from the next June.
At a glance
One seasonJanFebMarAprMayJunJulAugSepOctNovDec
Top 5 peak days each season, June 1 to September 30, any day, measured hourly. Measured on ComEd transmission zone load, in Eastern time.
What we forecast
This program has no forecast of its own. Its two parts are forecast by the PJM 5CP and ComEd transmission programs.
Where the forecast simplifies
- How much of the difference is added is set after the summer from every customer's loads, so it cannot be known ahead.
Sources
- The rulePJM OATT Attachment M-2 (ComEd), eTariff section 18111 ↗PJM / ComEd (FERC eTariff)
- PJM's official peaksSummer 2025 Weather Normalized RTO Coincident Peaks and 5CP, by zone ↗PJM
- PJM's five peaksPJM Manual 19: Load Forecasting and Analysis, Rev. 39 ↗PJM